theofficeofnilsjohansson

Risk Assessment — Pressure Vessel Maintenance Programme

   
Document No. JDS-RPT-MEC-002
Revision B
Date 2026-03-25
Status EXAMPLE
Author Nils Johansson
Project JDS-PRJ-MEC-001

1. Summary

This risk assessment identifies and evaluates hazards associated with the ongoing maintenance and inspection of pressure vessels at the Göteborg Workshop. It covers normal operations, inspection activities, and foreseeable failure modes. Controls are proposed following the hierarchy of elimination, substitution, engineering controls, administrative controls, and PPE.

2. Scope

3. Methodology

Risk is assessed using a 5×5 matrix per ISO 31000 and SS-EN 16991:

Likelihood (L):

Score Description Frequency
1 Rare Less than once per 20 years
2 Unlikely Once per 10–20 years
3 Possible Once per 5–10 years
4 Likely Once per 1–5 years
5 Almost certain More than once per year

Consequence (C):

Score Description Impact
1 Negligible No injury, minor repair
2 Minor First aid, localised damage
3 Moderate Medical treatment, partial shutdown
4 Major Serious injury, extended shutdown
5 Catastrophic Fatality, facility loss

Risk Rating = L × C

Rating Category Action Required
1–4 Low Monitor, no immediate action
5–9 Medium Controls required within 3 months
10–15 High Controls required within 1 month
16–25 Critical Stop work, immediate action

4. Risk Register

4.1 Hazard Identification — Operational

ID Hazard Cause Consequence
R-001 Overpressure event Relief valve failure, blocked outlet Vessel rupture, projectiles, blast
R-002 Corrosion-induced wall thinning Internal corrosion, condensate accumulation Leak or burst at weakened point
R-003 Steam boiler dry firing Low water level, level gauge failure Boiler tube failure, steam release
R-004 Hydraulic accumulator bladder failure Fatigue, over-cycling Sudden pressure loss, press malfunction
R-005 Nitrogen cylinder bank leak Fitting failure, impact damage Oxygen displacement in confined gas store

4.1b Risk Evaluation & Controls — Operational

ID L C Risk Controls Residual
R-001 2 5 10 HIGH Relief valve testing per schedule, pressure switch backup (PS-001), operator training 4 MED
R-002 3 4 12 HIGH Internal revision inspections per AFS 2017:3, UT thickness measurements, drain condensate weekly 6 MED
R-003 2 5 10 HIGH Low water cutoff device, daily water level checks, annual boiler inspection by DNV 4 MED
R-004 3 3 9 MED Pre-charge pressure checks quarterly, bladder replacement at 5-year interval 4 LOW
R-005 2 4 8 MED O₂ monitoring alarm in gas store, ventilation, restricted access, cylinder restraints 4 LOW

4.2 Hazard Identification — Maintenance Activities

ID Hazard Cause Consequence
R-006 Stored energy release during maintenance Incomplete depressurisation, isolation failure Burns, impact injury
R-007 Confined space entry (vessel internal inspection) Oxygen depletion, toxic atmosphere Asphyxiation, poisoning
R-008 Lifting injury during safety valve removal Heavy components, awkward access Musculoskeletal injury
R-009 Chemical exposure during cleaning Descaling agents, degreasing solvents Skin/eye irritation, fume inhalation

4.2b Risk Evaluation & Controls — Maintenance Activities

ID L C Risk Controls Residual
R-006 2 4 8 MED Lock-out/tag-out procedure, double block and bleed, pressure gauge verification at zero 3 LOW
R-007 2 5 10 HIGH Confined space permit, gas testing, standby person, rescue plan, ventilation 4 MED
R-008 3 2 6 MED Mechanical lifting aids, two-person lift policy, pre-task briefing 2 LOW
R-009 3 2 6 MED SDS review, PPE (gloves, goggles, respirator), local exhaust ventilation 2 LOW

5. Risk Matrix Summary

  Negligible (1) Minor (2) Moderate (3) Major (4) Catastrophic (5)
Almost certain (5)          
Likely (4)          
Possible (3)   R-008, R-009 R-004 R-002  
Unlikely (2)       R-005, R-006 R-001, R-003, R-007
Rare (1)          

6. Conclusions

7. Recommendations

Priority Action Responsible Target Date
High Install O₂ depletion alarm in gas store (R-005) Facility manager 2026-Q2
High Develop confined space rescue plan (R-007) Safety officer 2026-Q2
Medium Establish UT thickness baseline for PV-001 and PV-004 (R-002) Inspection contractor 2026-Q3
Medium Procure mechanical lifting aid for valve workshop (R-008) Workshop supervisor 2026-Q3
Low Review and update SDS file for all maintenance chemicals (R-009) Nils Johansson 2026-Q4

Revision History

Rev Date Author Description
A 2026-03-25 Nils Johansson Example risk assessment for JDS demonstration
B 2026-03-25 Nils Johansson Split 9-column risk register into hazard identification + risk evaluation tables (max 7 cols for A4)